Housekeeping Department’s Newbuild Setup

With approximately one more month to go before the official delivery of Eurodam, it is a good time to inform our Eurodam Blog readers about the newbuild set-up conducted by the Housekeeping Department.

One of the largest assignments of the Eurodam housekeeping newbuild team is the inspections of the staterooms. I will go into detail about these stateroom inspections in my next post, but first I want to briefly describe the way a stateroom is constructed.

All staterooms consist of two main areas: the bedroom and the bathroom.

In the photo you see some prefabricated bathroom units located on the pier, ready to be lifted on to the ship.


The bedrooms are constructed inside the ship. First, all wires and pipes are installed; after that, the walls are put in place.


After the walls are in position, the ceiling is installed.


When the ceiling and walls are in position, the larger pieces of furniture are placed and mounted to the floor or wall. After that, it is time for the carpet.


All smaller pieces of furniture (beds, nightstands, sofa, etc.) are placed in the stateroom. In the photo you can see the parts of the sofa are still in boxes.


At this point the staterooms are almost ready. Mattresses are placed and smaller items like artwork, bed lights, curtains, etc., are installed.


Once the signage and outlet covers are installed, the stateroom is ready to be turned over to Holland America Line.